The construction of a new $25 million Waste Water Treatment Plant for the city of York, Nebraska located on 35 acre plot outside the city a few miles to the east began in March 22, 2017 and so far is on schedule for completion in the spring of 2019.

When this project for the city is completely finished they will have an aeration building that will be 156′ x 108′ in size and 17′ deep, enough to hold 2.1 million gallons. Along with the Aeration basin there will be the headworks building, a secondary treatment building, secondary clarifiers, a disinfection contact basin, a biosoilds holding tank and an operations building. Also, there are 2.6 acres of land on the western portion of the property that will have five reed bed areas that will be specially established to catch any possible leaching (from sludge) so the material can be taken back to the disinfection basin. The reeds will consume the sludge in a natural, biological way.

Approximately 7,000 cubic yards of concrete will be used for the building structures. With 75% of the Concrete in place, Overland Ready Mix in York has provided Hawkin’s Construction, who is doing all the work on this project, with 7,100 cubic yards of concrete and approximately 1,667 tons of fill sand.

This new Treatment Plant should give the City of York a minimum of 50 years and can easily be expanded to 100 years with upgrades.